OTTAWA RIVER BRIDGE – 2013
On bridge over Ottawa river, between L'ile Perrot and Sainte-Anne-de-Bellevue, three 32m TPG double track spans built in the...
On bridge over Ottawa river, between L’ile Perrot and Sainte-Anne-de-Bellevue, three 32m TPG double track spans built in the beginning of the century needed to be replaced. Techni-Gestion produced all the engineering drawings for the replacement of theses spans. The types of spans chosen were two double track with direct fixation TPGs and a twin […]
Replacement of four 176’-9 c/c Through Truss Spans and one 356’-6 c/c Swing Through Truss span with six new 176’-9 Through Truss spans. The mandate included production of engineering drawings for the Truss spans, detailed drawings and field details of the falsework for the removal of the Swing span, fall protection details for bridge inspectors, […]
The 64.7m double track TT Span of this bridge was replaced in 2000 with four DPG Spans supported on one additional pier. The pier had been built one year before. TECHNI-GESTION J.C. produced all the engineering drawings for the spans and the construction drawings for the pier. See also span replacement in 2013 at the […]